Slovnaft Refinery Upgrade Project

Slovnaft Refinery Upgrade Project

Mol Hungarian Oil & Gas | Czech Republic

Challenge

Numerous pipes, pipe racks, water and steam vessels and two large silos required pipe freeze protection and temperature maintenance of 30°C.

Solution

nVent  installed 2,500 meters of heat-tracing cables, multiple circuits, and associated controllers within an eight week timeline.